Timetable

Construction Timetable

August 2008: Pre-construction work on Ground Floor.

December 22, 2008:  Construction begins; South entrance closed indefinitely

January 2009:  Build temporary interior walls; begin demolition

Febraruy 2009:  Demolition continues; excavation begins

March-May 2009:  Excavation completed; core drilling and pouring for piers; design work on decorative screen panel

June-July 2009:  Foundation walls and floor slab poured; mock-up of building exterier and decorative screen construction begins

August-October 2009:  Structural steel erection; architectural review and approval of mock-up; interior and exterior walls, roof, and floor slabs poured; backfill foundation; construction and planting of green roof

November-December 2009:  Complete storm sewer lines, HVAC, plumbing and electrical; finish interior spaces; masonry work; exterior frames, install decorative screen panels; remove temporary interior walls and re-furbish

December 2009-March 2010:  Delivery and installation of robot racks, rails, and masts; installation of computer systems

April-June 2010:  Delivery and installation of bins and shelving units; interface of robot system to library system; system testing; staff training

 

Planning for Next Phase

October 2009-March 2010:  Design development of Information Commons renovation on 1st floor.